The Data Center Insurance Checklist: What Underwriters Ask For

A data center insurance submission usually needs a statement of values, electrical and redundancy documentation, a fire protection narrative, battery storage details, loss history, a business interruption worksheet, key contracts, maintenance and commissioning records, and natural catastrophe siting data. A complete, consistent package helps underwriters assess the risk and determine whether, and on what terms, they can offer coverage.
This checklist covers each item, why underwriters ask for it and what tends to slow a submission down. It applies to operators, developers and owners preparing a new placement or renewal. Exact requirements vary by insurer, coverage line and project, so treat this as a starting point to confirm with your broker.
This checklist focuses on property, equipment breakdown, business interruption and construction-related underwriting. Cyber, professional liability, general liability and management liability may require separate applications and supporting information.
The submission package, item by item
Keep the assumptions and valuation dates in the SOV, BI worksheet and supporting documents consistent, and explain any differences in the figures.
Four items that commonly stall a submission
- Values that don't reconcile. Values should reconcile, not necessarily match. Explain differences between replacement-cost values, construction budgets, financing amounts and BI projections. Use consistent site names, valuation dates, ownership assumptions and equipment schedules so underwriters can understand how the figures relate.
- A BI worksheet without dependencies. A single revenue figure isn't enough. Underwriters want to see which revenue depends on which systems and suppliers, and how long each would take to restore given current equipment lead times.
- Thin fire protection and BESS detail. A one-line description such as "fully sprinklered" won't answer the questions underwriters have about suppression type, compartmentalization and battery siting. Expect follow-up questions if the detail is missing.
- Loss runs requested too late. Loss runs come from prior insurers and can take time to arrive. Request them as soon as you start the process.
What a risk engineering visit looks at
For larger sites, an insurer's risk engineer will often visit or review the site before quoting or at renewal. Engineering scrutiny has grown sharply: Zurich says its risk engineers' annual hours on data center reviews rose 500% from 2020 to 2025 (Risk & Insurance).
A visit typically covers:
- Power path. Utility feeds, switchgear, transformers, UPS and battery rooms, generators and fuel storage, and how they're separated and protected.
- Cooling. Chillers, cooling towers, computer room air conditioning (CRAC) and computer room air handling (CRAH) units, liquid cooling loops and leak detection.
- Fire protection. Detection and suppression systems, fire separation, and impairment procedures when systems are offline.
- Housekeeping and operations. Combustible storage, hot work permits, contractor controls and change management.
- Maintenance practice. Whether testing and maintenance records match what's on site.
- Exposure. Neighboring properties, flood and storm defenses, and site security.
Have your facilities lead and someone who knows the maintenance records on hand. Recommendations from the visit may affect terms, so ask how they'll be reported and what timeline you'll have to respond.
How far ahead to start
The larger the program, the earlier you need to begin. A placement spread across many insurers takes longer than one with a single insurer, and engineering reviews add time.
As planning targets to confirm with your broker, not guaranteed lead times:
- Straightforward renewals: start gathering documents about three to four months before the renewal date.
- Large or multi-insurer programs: start earlier, often four to six months out, to leave time for engineering visits and for marketing the program to enough insurers to fill the limits.
- New construction: involve your broker during design, well before construction starts. Builder's risk and delay in start-up (DSU) terms depend on the construction schedule, commissioning plan, equipment lead times and projected financial exposure.
Start with the core documents and reconciled values, then agree the marketing and engineering sequence with your broker. Insurer discussions, site reviews and follow-up information requests may run in parallel. Starting late usually means fewer insurers have time to look at the risk.
Frequently asked questions
What do insurers need to quote a data center?
Insurers commonly request a statement of values, electrical and redundancy documentation, a fire protection narrative, UPS battery and energy storage details, a business interruption worksheet, key contracts, maintenance and commissioning records, and natural catastrophe information. They may also request five years of insurer-issued loss runs, where available, plus a separate record of significant outages and corrective actions. New entities or facilities should provide the available history and explain any gaps. Exact requirements vary by insurer, coverage line and project.
What is a statement of values for a data center?
A statement of values identifies the property and values proposed for insurance at each location, usually including buildings and equipment. Depending on the insurer's format, BI or other time-element values may appear on the same schedule or in a separate worksheet. Supporting details may include construction type, occupancy and MW of critical load.
Does Uptime Institute Tier certification lower my premium?
It can help underwriters assess resilience, but it isn't a guarantee of better terms. Underwriters still look at engineering, maintenance records, fire protection and loss history.
How long does a data center insurance submission take?
It depends on the program's size and how complete the documents are. Larger programs placed across many insurers, or those needing an engineering visit, take longer. Start early and request loss runs first.
Do I need a risk engineering visit?
Often, for larger or higher-value sites. The insurer decides based on values, exposure and what the submission shows. Complete records and knowledgeable site personnel can reduce follow-up questions and help the engineer assess the risk. Any effect on pricing, coverage or required improvements depends on the findings and the insurer.
Talk to a Fullsteam advisor
Preparing a submission or renewal? Talk to a Fullsteam advisor
This article is general information, not insurance, legal or financial advice. Submission requirements, coverage, pricing and availability vary by insurer, location, policy wording and the facts of each risk.